The Halton Hills Generating Station: the 265-megawatt expansion request, Council's answer and how IESO contracts are won
Atura Power asked the Town in 2023 to back a new gas turbine of up to 265 megawatts at its Steeles Avenue plant. Council declined. This reference page sets out each party's role, the IESO process and the published record as of October 25, 2026.
The details
The plant today
The Halton Hills Generating Station is a natural gas power plant at Sixth Line and Steeles Avenue. The Independent Electricity System Operator (IESO), which runs Ontario's power grid and buys new electricity supply, lists its owner as Portlands Energy Centre L.P., operating as Atura Power. IESO's records give the plant's size in more than one way, depending on the document.
- Natural gas; Sixth Line and Steeles Avenue, as described in Town Council's December 11, 2023 minutes
- 705 megawatts (MW) is listed against the station
- Average capacity of 641.5 MW with a 31.5 MW upgrade; contract end date April 2035 (IESO table dated September 18, 2023)
- IESO's Hydrogen Innovation Fund lists a 2023-contracted pilot to blend up to 15% hydrogen with natural gas in two combined-cycle units, total cost $12,641,900, status open
The 2023 expansion request
In 2023 the IESO ran a procurement called the Long-Term 1 Request for Proposals, or LT1 RFP, to buy year-round electricity capacity that would come into service between 2026 and 2028. Proponents' submissions included a form for evidence of municipal support. Atura Power asked the Town for a 'Municipal Support Resolution' for what Council's minutes describe as a proposed new natural gas turbine generator expansion, an LT1 reliability project of up to 265 MW, at the existing plant.
The request came to Council's General Committee on December 11, 2023 as staff report ADMIN-2023-036. The minutes list 17 delegations on the item. Brad Kyte of Atura Power spoke for the proponent, and Chuck Farmer spoke for the IESO. The others were residents and organizations, including The Atmospheric Fund, Ontario Clean Air Alliance and Environmental Defence. The minutes name the speakers and their subject but do not summarize what each said.
Where each party stood
- Asked the Town for a municipal support resolution for up to 265 MW of new gas generation at the existing station, and delegated to Council on December 11, 2023 (Council minutes)
- Adopted the General Committee recommendation, as amended, that the request for a Municipal Support Resolution 'not be granted to Atura Power' (Resolution 2023-0243; minutes do not print a vote count)
- Carried Resolution 2022-0133 as amended. As moved, it said Council would continue to support natural gas plants until a clean source can replace them without dramatically increasing electricity prices. The minutes do not spell out the amendment
- Runs the procurement and awards the contracts. It presented to Council on December 11, 2023; its LT1 page says the procurement produced competitive prices, municipal support and Indigenous participation
The two Council decisions answer different questions. The 2022 motion concerned whether gas plants should be phased out province-wide, while the 2023 decision concerned one request to back an expansion at one site. The minutes of the December 2023 meeting record the outcome but not Council's reasons.
How the IESO process works
Done: IESO posts the LT1 RFP
September 29, 2023, with prescribed forms including Evidence of Municipal Support.
Done: Council considers the support request
December 11, 2023: request not granted, as the minutes record.
Done: IESO concludes LT1
IESO's final results table is dated April 17, 2026. It lists 13 selected proponents and about 2,195 MW of new capacity, including 410 MW from natural gas and biogas.
Now: LT2 windows continue
IESO executed LT2 window 1 contracts for 1,115.10 MW (energy) and 640.00 MW (capacity), and posted draft documents for window 2 on October 9, 2026.
IESO, not a municipality, decides which proposals win a contract; evidence of municipal support was one of the items LT1 proponents submitted. Other approvals a power plant needs, such as environmental and building approvals, are separate and are not covered here.
What the record shows on October 25, 2026
IESO's LT1 final results table does not list a Halton Hills Generating Station expansion. Its only natural gas project from Atura Power is the Napanee Generating Station Expansion, at 430 MW nameplate capacity with a 405 MW contract capacity. The LT2 window 1 energy and capacity result tables list neither Halton Hills nor Atura. The Town's Council minutes read for this page show no later request for municipal support for an expansion.
That is the state of the published record, and it does not say whether Atura Power or another proponent will propose an expansion in a later procurement window. Council's agendas and minutes, linked below, are where any future request would appear.
Where to check
- Council agendas, minutes and video: the Municipal Calendar at calendar.haltonhills.ca/meetings, which links to the Town's eSCRIBE agenda site.
- IESO procurements and results: the Long-Term 1 RFP and Long-Term 2 RFP pages under Resource Acquisition and Contracts at ieso.ca.
- Speaking to Council: the Town's delegation process is covered in the Wards and Council guide on this site.
Sources
Town of Halton Hills
Council - December 11, 2023: Post-Meeting MinutesTown of Halton Hills
Council Meeting - July 4, 2022: MinutesIndependent Electricity System Operator
Long-Term 1 RFP and Expedited ProcessIndependent Electricity System Operator
Long-Term RFP (LT1 RFP) - Final ResultsIndependent Electricity System Operator
Long-Term 2 RFPIndependent Electricity System Operator
Long-Term 2 Energy Supply (Window 1) RFP - Final ResultsIndependent Electricity System Operator
LT2(c-1) RFP final results tableIndependent Electricity System Operator
Same Technology Upgrades Solicitation - Executed AgreementsIndependent Electricity System Operator
Halton Hills Hydrogen Blending: Hydrogen Innovation Fund Project DetailsIndependent Electricity System Operator
Transmission-Connected Resources