Three Halton Hills housing proposals totalling 2,307 homes now sit with the Ontario Land Tribunal, not Council
The applicants for towers at 130 Mountainview Road North, a 744-home subdivision on 10 Side Road and 82 homes on Confederation Street in Glen Williams appealed after the Town did not decide within 120 days. The Tribunal will now make the decisions.
The details
Why these are at the Tribunal
Under the Planning Act, an applicant can appeal to the Ontario Land Tribunal if a municipality has not decided an application within 120 days of deeming it complete. According to the Town's project pages, the applicants for three residential proposals in Georgetown and Glen Williams have done so. Together the three propose 2,307 homes.
- 1,481 units in six towers of 17 to 22 storeys; appealed September 2025
- 744 homes plus a mixed-use block; appealed November 2025
- 81 townhouses and one detached house; appealed May 2025
130 Mountainview Road North
Gilbach Georgetown Inc. applied in late December 2024 for Official Plan, zoning and draft plan of subdivision approvals for three apartment buildings containing six towers, ranging from 17 to 22 storeys, with 1,481 units. The plan includes a new public road connecting River Drive with Mountainview Road, ground-floor commercial space in the building closest to River Drive and Mountainview Road North, a privately owned park open to the public, and 1,481 parking spaces inside the buildings and underground.
The applicant appealed in September 2025. The Town's page says the Town is awaiting formal direction from the Tribunal on next steps.
16469 10 Side Road
Russell Pines Property Corp. applied in April 2025 for zoning and draft plan of subdivision approvals in the Southeast Georgetown Secondary Plan area. The plan shows 274 single detached lots and 470 townhouses, two neighbourhood parks, a parkette, a stormwater pond and a mixed-use block where at least 1,800 square metres of commercial space must be built first. About 5.1 hectares outside the urban boundary would be given to the Town for a recreational trail and to protect natural features.
A statutory public meeting was scheduled for June 16, 2025, and the applicant appealed in November 2025. The Town's page says it is awaiting further instructions from the Tribunal.
159 Confederation Street, Glen Williams
Eden Oak (Bayfield) Inc. applied in December 2024 for 81 two-storey townhouses in 15 blocks and one single detached house on a new private condominium road, with four parking spaces per unit, 26 visitor spaces and two parkettes. A statutory public meeting was held on March 24, 2025, and the applicant appealed in May 2025. The Tribunal scheduled a case management conference for October 24, 2025. The Town's page reports nothing about the case after that.
How residents can take part
The Town's page for 130 Mountainview Road North explains how the Tribunal process works. Anyone who wants to take part as a party or a participant must send the Tribunal's request form to its assigned case coordinator 10 days before a case management conference, and must attend that conference, where the presiding Tribunal member considers the requests. The conference is also where issues, the hearing's procedure, possible mediation or settlement, and hearing dates are discussed.
Sources
Town of Halton Hills
130 Mountainview Road North development proposalTown of Halton Hills
16469 10 Side Road, Southeast Georgetown development proposalTown of Halton Hills
159 Confederation Street, Glen Williams development proposal