Halton Hills awarded more than $7 million in 2026 road contracts for resurfacing, Ontario and Ann streets and Glen Lawson Road
On March 30, 2026, Council's General Committee awarded the year's pavement resurfacing tender and two reconstruction contracts, covering 14 named streets in Acton, Georgetown and the rural area plus Ontario Street, Ann Street and Glen Lawson Road.
The details
What Council awarded on March 30
Halton Hills Council's General Committee awarded three road construction contracts on March 30, 2026, and Council adopted them the same day as immediate action items, the minutes show. Together the three base awards come to about $7.1 million before tax. All three resolutions carried.
- Forest Contractors Limited, $3,321,651.24. Purchase order authorized at $3,608,653.32, plus a $326,257.86 contingency, for $3,934,911.18 in all.
- MGI Construction Corp, $2,254,216.90. A separate purchase order of $258,872.00 was authorized to Gannet Fleming Canada ULC.
- Forest Contractors Limited, $1,542,646.59, described as the lowest compliant bid, plus a $150,000 contingency, for $1,692,646.59 in all.
The Glen Lawson Road award was conditional. The resolution let the Town's procurement manager award the tender once engineering staff confirmed that all required permits and approvals were in place.
The streets on the resurfacing list
The Town published the resurfacing list on February 10 under the ROADS 2026 banner, saying work would start in the spring in Wards 1, 2 and 3. Twelve streets were listed for resurfacing and two for minor reconstruction.
- Beacon Gate, from Jason Crescent to the end
- Cameron Street, from Mill Street East to the end
- Chantelay Crescent, from 15 Side Road to the end
- Clare Court, from Division Street to the end
- Division Street, from Wallace Street to McDonald Boulevard
- George Street, from Mill Street to Division Street
- Halton Hills Drive, from Maple Avenue to Princess Anne Drive
- Holmesway Place, from Cobblehill Road to the end (minor reconstruction)
- Jason Crescent, from Ontario Street to Jason Crescent
- Maple Avenue East, from Maple Avenue to the end
- Market Street, from Wesleyan Street to Mill Street
- McDonald Boulevard, from Wallace Street to Churchill Road
- Tenth Line, from 22 Side Road to 0.3 kilometres south
- 10 Side Road, from Regional Road 25 to Third Line (minor reconstruction)
The Town said pavement management has been an annual program since 2003, that its own staff supervise the work, and that residents on affected streets are notified before work starts. A comment period on the Let's Talk Halton Hills project page ran from February 9 to 20.
Next in line: McNabb Street and Mill Street
On May 11, Council awarded the engineering design for a future reconstruction of McNabb Street and Mill Street, including the rehabilitation of a culvert the Town identifies as 50/C, to WF Group Inc. of Kitchener for $232,169 before HST, with a $25,000 contingency. That contract is for design only. The minutes set no construction date.
Where the work stands
The Town's closure notices show the reconstruction contracts still under way in the fall, all with Forest Contractors as the contractor. On September 29 the Town said Glen Lawson Road work was moving to a second phase, closing Glen Lawson Road between Third Line and Fourth Line from an expected October 5 to an expected November 6. On October 15 it said the 10 Side Road closure between Regional Road 25 and the CN tracks needed two more days, October 19 and 20, because of delays in getting CN flagging. On October 23 it gave notice of a Tenth Line closure between 20 Side Road and 22 Side Road from an expected November 4 to November 6. As of November 10, 2026, the Town had not published a notice saying any of the 2026 contracts was complete.
Sources
Town of Halton Hills
ROADS 2026 Resurfacing Focuses on Wards 1, 2 and 3Town of Halton Hills
Minutes, Council Meeting, May 11, 2026 (Report TPW-2026-010)Town of Halton Hills
NOTICE OF ROAD CLOSURE: Glen Lawson Road ReconstructionTown of Halton Hills
ROAD CLOSURE UPDATE: 10 Side Road, RR25 to Third Line STown of Halton Hills
NOTICE OF ROAD CLOSURE: Tenth Line, 20 Side Road to 22 Side Road