Overflow parking lot for Toronto Premium Outlets proposed at 13495 and 13571 Steeles Avenue; public meeting December 14
A temporary use by-law would allow a parking lot at 13495 and 13571 Steeles Avenue to serve as overflow parking during construction at Toronto Premium Outlets for up to three years. Halton Hills Council hears from the public on December 14 at 6 p.m.
The details
What is proposed
The Town of Halton Hills has received an application for a temporary use by-law, a form of zoning amendment, covering 13495 and 13571 Steeles Avenue in the Premier Gateway Employment Area. According to the Town's notice, dated November 13, 2026, the purpose is to permit a parking lot to be used as overflow parking during construction activities at Toronto Premium Outlets, for a period of up to three years.
A temporary use by-law allows a use that the zoning would not otherwise permit, for a limited time. The notice includes an air photo of the location and a site plan drawing of the temporary parking lot.
- Zoning By-law Amendment (Temporary Use By-law)
- 13495 and 13571 Steeles Avenue, Premier Gateway Employment Area
- Overflow parking during construction activities at Toronto Premium Outlets
- Up to three years
- Monday, December 14, 2026, 6 p.m., before Council
- Town planning staff, 905-873-2600 ext. 2979
The public meeting
Council will hold a statutory public meeting on the application on Monday, December 14, 2026, at 6 p.m. at Town Hall, 1 Halton Hills Drive, Georgetown. The meeting is hybrid: residents can attend in person or join by Zoom or by phone, using the link and numbers in the Town's notice. The Town says the meeting is an opportunity for the public to ask questions or give their views on the proposal.
A statutory public meeting is where Council hears the proposal and public comments before staff bring back a recommendation; Council does not decide the application at that meeting. The notice says information about appeal rights is available from the Town's planning staff.
What the notice does not say
The notice does not name the applicant, give a file number, say how many vehicles the lot would hold, or describe the construction at Toronto Premium Outlets that the overflow parking is meant to support. It also does not say how shoppers would get between the lot and the outlet centre. Those details would normally be set out in the staff report for the December 14 meeting, which had not been posted when the notice was read on November 17.