Halton Hills starts planning 272 hectares of new Premier Gateway employment land between Sixth Line and Eighth Line

The Town has begun a secondary plan for the Brownridge Premier Gateway Phase 3 West lands, north of the existing Phase 1B employment area. The work runs in five phases from fall 2026 and is expected to finish in late fall 2028.

HaltonHillsIQ Newsroom3 sources · 2 min read

Email

The details

What the Town is planning

The Town of Halton Hills is preparing a secondary plan for the Brownridge Premier Gateway Phase 3 West area. The Town says the area covers about 272 hectares from Sixth Line to Eighth Line, north of the existing Premier Gateway Phase 1B employment lands.

The Town calls the Premier Gateway its prestige employment area, extending north from Highway 401, where large-scale employment growth is to be directed. It is planned for new office, warehousing, manufacturing and commercial development. Planning began in 2000 between Highway 401 and Steeles Avenue, and the area has since grown into second and third phases between Sixth Line and Winston Churchill Boulevard.

The Town says this project begins long-term planning for the newest expansion of the Premier Gateway Employment Area, which came about through Halton Region Official Plan Amendment 49.

Where it is

The Town's Notice of Commencement map shows the study boundary running from Sixth Line east to Eighth Line and straddling Trafalgar Road, north of the Phase 1B employment lands and south of 5 Side Road. On that map, most of the land inside the boundary is shaded as Agricultural Area, and several Greenlands corridors cross it.

What the study will look at

  • A land use plan for the employment lands, guided by the Provincial Planning Statement.
  • The transportation and servicing needs of the current and future population.
  • Cultural heritage and urban design, in support of a preferred land use plan.
  • A Scoped Subwatershed Study to confirm the extent of the Natural Heritage System in the area, which the Town says will be the basis for protecting natural heritage resources in the expanded Premier Gateway.

Timeline

The five phases, as set out on the Town's Let's Talk Halton Hills project page
  1. Now: Phase 1: Fall 2026 to winter 2027

    Project initiation and background review. The Town lists this as the current stage.

  2. Next: Phase 2: Winter to spring 2027

    Subwatershed and Natural Heritage System planning.

  3. Next: Phase 3: Summer to fall 2027

    Detailed planning study.

  4. Next: Phase 4: Winter to spring 2028

    Recommended and then preferred land use options.

  5. Next: Phase 5: Summer to fall 2028

    Draft and then final secondary plan.

The Town expects the secondary plan to be completed in late fall 2028. Residents can register on the project's Let's Talk Halton Hills page, letstalkhaltonhills.ca/bpg, to follow public engagement opportunities as they are announced.

Sources

Every factual claim above traces to one of these documents.

  1. Town of Halton Hills

    Premier Gateway Employment Area Secondary Plans

    Retrieved October 9, 2026

  2. Town of Halton Hills

    Brownridge Premier Gateway Phase 3 West Secondary Plan

    Retrieved October 9, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.


Go deeper

All stories